BUNGE TURKEY –Commissioning of the Prepressing Unit, which was erected by HUM at Aliağa facilities, started in May 2011

Turn-key basis contract...

April 2011

BUNGE TURKEY –Commissioning of the Prepressing Unit, which was erected by HUM at Aliağa facilities, started in May 2011

The prepress unit with a sunflower seed processing capacity of 600 tons/day was ordered on turnkey basis including the services of engineering, equipment supply, assembly and commissioning. This unit was added to the existing soy plant, thus it is now possible to process sunflower seed and canola processing.

BUNGE TURKEY –Commissioning of the Prepressing Unit, which was erected by HUM at Aliağa facilities, started in May 2011